Mainstream maintenance for SAP ECC 6.0 ends in 2027. Many companies are therefore planning the move to S/4HANA. What is often underestimated is how much work sits in their own developments. Here you will find the deadlines, an example from our practice and a roadmap for the next steps.
The deadlines at a glance
Maintenance ends in stages. Which stage applies to you also depends on your system’s enhancement package.
| Date | What happens |
|---|---|
| 31 Dec 2025 | Mainstream maintenance for SAP ERP 6.0 on enhancement packages 0 to 5 has already ended. Extended maintenance is not available for these systems. |
| 31 Dec 2027 | Mainstream maintenance for SAP ERP 6.0 on enhancement packages 6 to 8 ends. |
| 2028 to 2030 | Extended maintenance at extra cost: two percentage points on the maintenance base. |
| 2031 to 2033 | “SAP ERP, private edition, transition option”, only for RISE with SAP customers under strict conditions. |
The option until 2033 comes with strict requirements. The system must be migrated to SAP ERP, private edition on SAP HANA by the end of 2030 and be at least 2 TB in size. The paid “Max Success Plan” is also required. For many mid-sized companies this is not a realistic alternative. Their planning horizon remains 2027, or 2030 at the latest.
Why custom code is the bottleneck
S/4HANA is not a simple upgrade. The data model has been simplified: tables have been merged or removed, and some functions work differently. SAP adapts the SAP standard itself. Your own developments are yours to check: every Z program, every enhancement and every interface that accesses old structures.
On top of that, hardly any company knows exactly how many custom developments its system contains. Even fewer know which of them are actually used.
Five questions to ask now
- How many custom developments are running, and which are actually used? Usage data (e.g. from SCMON or SUSG) shows which programs nobody has called for a long time. What isn’t migrated doesn’t need to be reworked.
- Have the S/4HANA checks been run on your custom code? The ABAP Test Cockpit (ATC) with its S/4HANA check variants shows which parts of the code conflict with the new data model.
- Do you know all your interfaces and their dependencies? IDoc, BAPI, RFC and file interfaces often hide dependencies that only surface during testing.
- Which custom developments can be replaced by standard functions or Fiori apps? Whatever the standard covers, you won’t have to maintain yourself later.
- Does the migration have a schedule, an owner and a test window? How long rework and testing take depends on the amount of code. Starting late leaves little time for testing.
A realistic roadmap
Much of the work can be done before the actual migration project starts.
- Inventory: collect usage data over a full year so that month-end and year-end closings are included.
- Clean up: deactivate unused programs and merge duplicates.
- Check: analyse the remaining code with the S/4HANA checks in the ATC and rank the findings by effort and risk.
- Adapt: make the code HANA- and S/4HANA-ready step by step. Much of this can already be done in the existing system.
- Test: with test cases from the business departments, not just technically.
Conclusion
The 2027 date has been known for years. Even so, time is getting tight for many companies. Cleaning up and checking your custom code now buys you time: for deciding on your path to S/4HANA, for thorough testing, and as a buffer in case something in the project takes longer.
Let’s see together what’s possible.
Tell us briefly where your system stands. We’ll get back to you with an honest assessment.